Century Kindle Project Schedule and Timeline Details as of RERA
Century Kindle is a premium apartment project located in Yelahanka, North Bangalore. The project is registered under RERA (PRM/KA/RERA/1251/309/PR/200326/008542), which means it follows clear rules, proper approvals, and fixed timelines for construction. The construction starts with the Sub-Structure work, which includes foundation and basement work. After that, the Super-Structure work will continue, where the G+2B+19 floor building will be built step by step. Once the main structure is ready, the Finishing Works, like fittings, fixtures, painting, and interiors, will be completed. At the same time, work on Amenities and Common Areas will also be done so that everything will be ready together. As per the plan, the possession date is December 2029. By then, the project will be fully ready, so buyers can plan their purchase and move in easily.
Detailed Project Schedule Plan of Century Kindle as per RERA
The Century Kindle project schedule, as per RERA, shows a clear timeline of the construction work. It explains each stage, from foundation work to final finishing, in a simple way. Buyers can easily understand when each step will be completed and when the homes will be ready for possession.
Sub-Structure Work
The Sub-Structure stage at Century Kindle is the first step of construction and is very important for making the building strong. All the work in this stage is done below the ground to support the G+2B+19 floors. It helps the building stay safe and stable for a long time. This stage includes land preparation, foundation work, and basement construction, such as parking areas. A strong base makes sure the entire building above is safe and secure.
| Project Work | Estimated Start Date | Estimated Completion Date |
| Earthwork & Levelling | 01 March 2026 | 29 August 2026 |
| Foundation Footing Work | 16 June 2026 | 17 September 2026 |
| Up to Plinth Level | 22 July 2026 | 13 September 2027 |
| Sub-structure Flooring (Parking) | 05 December 2026 | 01 September 2027 |
| Retaining Wall (All types) | 05 December 2026 | 01 September 2027 |
Super-Structure Work
The Super-Structure stage at Century Kindle is the part of construction where the main building above the ground is built. After the foundation is ready, this stage forms the full shape of the building, including walls, floors, and interiors. It is an important stage because it turns the project into a visible structure and prepares it for final finishing.
| Project Work | Estimated Start Date | Estimated Completion Date |
| RCC or MS Framed Structure | 14 July 2027 | 05 March 2029 |
| Masonry Construction | 28 September 2028 | 25 June 2029 |
| Plastering inside, Outside & Ceiling | 27 March 2029 | 01 January 2030 |
| Joinery: Doors, Windows, Ventilators, etc. | 02 November 2029 | 18 October 2030 |
| Water Supply, Sanitary & Electrification | 08 January 2030 | 14 March 2031 |
| Dadoing, Skirting, Flooring & Tile Work | 08 April 2030 | 05 October 2030 |
| Railing and Grill Fixing | 01 January 2030 | 21 April 2030 |
Finishing Works (Fitting and Fixtures) Work
The Finishing Works stage at Century Kindle is where the building is turned into a ready-to-live home. In this stage, all the fittings and fixtures are completed so that each flat in the G+2B+19 floor building looks clean, complete, and comfortable. As per the RERA schedule, all this work is planned in a proper timeline to match the possession date of December 2029. Some final work, like water, electricity, and other systems, may continue till early 2031 to make sure everything is fully working and ready.
| Project Work | Estimated Start Date | Estimated Completion Date |
| Final Electrical, Water & Sanitary Finishing | 25 June 2029 | 15 February 2031 |
| Interior & Exterior Painting | 02 December 2029 | 18 October 2030 |
| Weather Proofing (Tile & Concrete) | 22 November 2029 | 27 December 2030 |
| Fire Safety Fitting, Fixtures & Network | 11 March 2030 | 06 November 2030 |
| Elevation Work (Exterior Look) | 02 March 2030 | 26 January 2031 |
| Internal & external work with landscaping | 22 December 2029 | 17 November 2030 |
Amenities Work
The Amenities at Century Kindle are planned to give a comfortable and modern lifestyle for all residents. These facilities are spread across a large area inside the project and include spaces for relaxation, fitness, fun, and daily needs. Everything is planned so that residents can enjoy a better and easy living experience.
| Amenities | Area (Sq Mt) |
| Parks and Green Spaces | 6,366.38 |
| Clubhouse | 3,067.61 |
| Water and Sanitation Infrastructure | 843.25 |
| Indoor Sports Facility | 779.37 |
| Community Hall | 580.00 |
| Gymnasium | 533.92 |
| Electricity/Substation Area | 444.90 |
| Outdoor Sports Facility | 325.00 |
| Swimming Pool | 287.64 |
| Power Backup (DG Sets) | 144.22 |
Common Areas Work
The Common Areas at Century Kindle are the shared spaces that all residents can use. These areas are not part of any one flat, but are important for movement, safety, and daily use inside the building. They help residents move easily, stay safe, and access basic services.
| Common Areas | Area (Sq Mt) |
| Staircases | 1,935.22 |
| Lifts | 909.48 |
| Corridors/Lobbies | 7,406.34 |
| Fire Escapes | 1,935.22 |
| Entrance/ Exit/Foyer/Verandah | 179.98 |
| Basement | 21,115.99 |
| Terrace | 132.78 |
| Outer Wall | 2,550.16 |
| Water Conservation & Renewable Energy | 0.01 |